How to start repair works regarding the apartment?
The initial stage of the particular repair of older apartments is the destruction and taking out first of just about all of the dilapidated wall space and partition surfaces, removing the wall structure and ceiling covering. This stage is one of the particular most “dirty” phases of the repair.
One more being among the most important and “dusty” performs is the window block replacement. You need to do this very first of all because dirt and dust particles is going to be unallowable in the course of following stages and it is forbidden at all to open windows during painting and picture works (large drops of the temp and moisture are usually unallowable). After installation windows and windowsills it is necessary to pack them immediately in polyethylene film and to cover windowsills inside addition by the fiberboard (in so that it will prevent scratches).
The following stage is wiring. Electrical wiring can be installed in walls or perhaps along the flooring. Wiring is manufactured inside the plumbing to ensure power safety and boost reliability. The pipe protects wiring from external damages and allows to change the wire completely without breaking walls and floor just by inserting the brand new wire instead of the old 1.
House Painting comes after the wiring. The particular frequent mistake during the simultaneous executing of such works occurs when staff forget to place out among the cabling and house artists have already plastered and smoothed out your wall. As the result, additional works are necessary to be able to seal chases on the finished wall. The particular places of the particular feed switch plus wall outlet area and the number should be thought-out in advance. The scheme of power electrical wiring is usually integrated to the design job.
Down the road the method must be prepared to service in situation of failures. Inside addition to the particular wirings, the telephone cable and the TELEVISION cable are organized. The power cable connection really should not be laid out there near the telephone and antenna cabling to avoid noises pickup and interference. Probably the most peculiar moment is laying away the TV cable. In order to make two (or three) TV sets in the apartment the second cable is frequently simply “firmly soldered” in parallel, so the cable level of resistance is lowered. Since a result, the display quality is damaged, many programs can’t be received in addition to etc. In buy to avoid such situation it is usually necessary to request a specialist with special equipment. This individual will measure the transmission level of typically the each TV-feeder plus install TV-amplifiers or even TV-filters.
Painting is the most long-term process, that is why it is conducted simultaneously in almost all premises, in case it is feasible. Delays are associated with the technological innovation. Each applied layer of the plaster (or filling within finishing) must dry completely prior to the function will continue.
Performs in sanitary preparations and the kitchen area begin simultaneously with house painting. It is advisable to fulfill alleged “dirty” works in the first location and simultaneously. Within accordance with the master plan of the sanitary technician location welding, wall chasing plus pipe run are conducted. Steam rad admissions are ready, taps and conference are mounted, yet radiators are certainly not mounted.
Then works in sanitary arrangements usually are conducted according to the program. The bath is usually mounted, then walls are smoothed out and the tile is laid about walls. The next stage is building ceiling and putting tiles on the particular floor. And at last other hygienic devices, mixers plus accessories are attached.
After wiring, installation of rosette dishes and terminal boxes the voltage will be checked in most point. Ends of cabling are insulated plus laid out into rosette plates. Electrical sockets and breakers are not installed during this specific stage in buy to save their own surface appearance. Typically the finish puttying regarding walls is performed simultaneously. The technically exact control over drying out of the layer of the plaster (filling) is taken out by drymeter. It is a special instrument that will measures moisture associated with the material.
The following stage is the means of fill. Fill up could be made with different materials – from usual brickwork cement-sand mixture to self-aligning floors. The advantage of the particular simple mixture is usually its cheapness, the particular disadvantage is that such mixture is usually much harder in-line at the stage and the last dry time associated with such fill will be 40 days, simply then the following stage of typically the work with floor may be conducted, i actually. e. the period is too long. Self-leveling self-aligning floors are more expensive, yet more technological. Aiming occurs almost “automatically” i. e. liquid solution of combination is poured out, then it operates and you get the horizontal area. The final dry time is two weeks i. e. you might have significant time overall economy. The system “warm floor” is mounted into the fill. If the so-called “wet processes” are inapplicable the technology of the dry aiming (the fill technology) is used facets for floors together with adjustable floor battens are mounted.
Following fill door bins and door are installed. Installation of entry doors must take in to the account density of future flooring. After installation the doorway can be taken off its handles and removed right up until the end associated with repair or jam-packed into polyethylene movie to protect from damages. Simultaneously ceiling can be painted plus the tile can be laid for the reason that premises where it absolutely was planned. The floor tile must be put on the absolutely dry out overlay.
Finishing regarding the floor mounting depends on the planned covering. Within most cases (if finish covering is not the tile) load is covered by simply bitumen mastic plus plywood sheets usually are laid. They usually are fixed to the ground by self-tapping anchoring screws. One plywood sheet is fixed simply by 30-50 self-tapping screws to provide the particular close fixing associated with plywood and long lasting service of the ground without squeak and bulging. The plywood gives the additional heat- and acoustic insulation. After increasing of the particle board is finished, wallpaper for painting can end up being pasted on surfaces.
In Ultimate complete detail paint restoration in North Carolina where finish covering of the floor will be laminated flooring or parquet hoard, the ordinary wallpapers are pasted (not for painting) in the very first place. Then the floor covering is mounted.
If finish addressing in the floor is the block parquet, the parquet is usually laid in the first place, after that it is scraped and covered by simply one layer associated with lacquer. After this particular the ordinary wall-papers are pasted plus the parquet is have the rest layers of lacquer (depending within the quality associated with the parquet in addition to lacquer). The mentioned consequence is associated only with these kinds of scrambling process whenever the great amount of dust is usually created. In spite of typically the fact that very good floor grinders are usually equipped with the vacuum cleaner, the particular sufficient amount regarding dust is brought on on surrounding subjects including walls. Dirt is very acerbic and is poorly washed off. That will is why to be able not to harm wallpapers, they usually are pasted after scrambling and in buy the parquet tend not to absorb the surplus moisture it is usually covered by the main one layer of ename before wallpaper pasting.
After this the main works could be considered in order to be finished. It is left just to install the plinths, decorative elements, breakers and sockets, drape holders, to hang doors, plant-bands in addition to others.
In summary this is necessary to be able to note that typically the sequence of works was listed inside general and may change according to the particular situation – the particular number of areas in premise, your current resources, peculiarities associated with the construction regarding the multilevel building. It is dependent on good sense and every person capable of analysis can individually create such a new sequence.